West Badger Rd/Bertrand Creek Bridge No. 50

W. Badger Project Location

Project Map 5.10

W. Badger/Bertrand Crk Bridge

Bridge 50

Project Pictures

Project Update for December 6, 2019



Whatcom County and Razz Construction are pleased to announce that West Badger Road at Bertrand Creek has been opened to traffic today, Friday, December 6. Please note that the detour signs on both the local detour and truck detour routes will be removed which includes the temporary stop signs installed at the Loomis Trail Road/Berthusen Road intersection. In addition, there may be intermittent flagged one lane closures over the next couple of weeks as final project details are wrapped up.

We would like to thank everyone again for your patience as we worked to complete this important bridge replacement project.


Project Update for November 25, 2019



Recently completed major work items include:

  • Structural earth retaining walls
  • Bridge traffic barrier
  • Bridge approach slabs
  • Approach roadway work
Upcoming major work items include:

  • Paving
  • Striping
  • Guard rail installation
  • Landscaping and planting
West Badger Road is closed just west of Berthusen Road during construction with signed local detour and truck detour routes in place. It is anticipated that West Badger Road will be re-opened to traffic in early to mid-December 2019.

Project Update for October 29, 2019


Recently completed major work items include:

  • Girder stops
  • Intermediate and end diaphragms
  • Placement of concrete deck
Upcoming major work items include;

  • Structural earth retaining walls
  • Bridge traffic barrier
  • Approach roadway work
  • Approach slabs
West Badger Road is closed just west of Berthusen Road during construction with signed local detour and truck detour routes in place. It is anticipated that West Badger Road will be re-opened to traffic in December 2019.


Project Update for October 2, 2019



Recently completed major work items include:
  • Scour protection rock
  • Concrete abutments and curtain walls
  • Removal of stream diversion
  • Setting of the new precast, pre-stressed concrete girders
Upcoming major work items include:
  • Girder stops
  • Intermediate and end diaphragms
  • Placement of concrete deck
West Badger Road is closed just west of Berthusen Road during construction with signed local detour and truck detour routes in place. It is anticipated that West Badger Road will be re-opened to traffic in December 2019.

Project Update for August 28, 2019


Major work items recently completed or currently being worked on include:

  • Installation of flood scour protection rock
  • Driving of foundation steel pipe piles
  • Concrete abutment forming and rebar placement
Upcoming major work items include:

  • Completion of flood scour protection rock
  • Pouring of concrete abutment pile caps and walls
  • Removal of stream diversion
  • Placement of prestressed concrete girders
West Badger Road is closed just west of Berthusen Road during construction with signed local detour and truck detour routes in place. It is anticipated that West Badger Road will be re-opened to traffic in December 2019.

Project Update for July 25, 2019



Recently completed major work items include:

  • Site preparation work
  • Installation of erosion control elements
  • Installation of stream diversion
  • Demolition of existing bridge deck
Upcoming major work items include:

  • Demolition of existing bridge foundation
  • Driving steel pipe piles for new bridge foundation
West Badger Road is closed just west of Berthusen Road during construction with signed local detour and truck detour routes in place. It is anticipated that West Badger Road will be re-opened to traffic in December 2019.

Project Update for June 6, 2019



Construction activities will begin on site on Monday, June 24th. Accordingly, West Badger Road at the project site will be closed beginning Monday, June 24th. At that time the signed detour routes will be signed and in effect. We anticipate the closure continuing through December 2019.

Project Update for May  10, 2019



Construction of this project is anticipated to start in late June and continue through December 2019. West Badger Road will be closed at this location during construction with signed detour routes in place for both local traffic and trucks.

The construction contract for this project has been awarded to Razz Construction, Inc.

Location:  West Badger Road at Bertrand Creek located approximately 1-mile west of Guide Meridian (SR 539).

Project Details: This project consists of replacing an existing 69-foot channel girder bridge on timber caps and pilesWork will also include approach slabs, roadway approach work and guard rail installation.

Project design, permitting and real estate work is complete and construction of this project is expected to begin in June 2019 and continue through December 2019.

Funding: $1,430,008 in Federal bridge funds have been obtained for construction of this project. Remaining funds needed to complete the project will come from the road fund.

Traffic Limitations: West Badger Road will be closed at this location during construction starting in June, 2019 and continuing through December, 2019. A signed detour will be in place during construction which will utilize Berthusen Road, Loomis Trail Road and Weidkamp Road for local traffic. The truck detour will include Guide Meridian (SR 539), Birch Bay Lynden Road and Sunrise Road.